Held a ceremony to celebrate four units of the Hyundai Green Power Steel Power Plant

DATE 2011.02.10

VIEW 485

Held a ceremony to celebrate four units of the Hyundai Green Power Steel Power Plant


 A ceremony to celebrate four units of the Hyundai Green Power Steel Power Plant with the participation of President Kim Yun of the Plant Business Division and other VIPs in and out of the company on December 15, 2010. The project aims to build an environment-friendly power plant which utilizes gas from an integrated steel mill. The project began in September, 2007. Unit #1 and Unit #2 successfully entered into commercial operation on March 25, 2010 and Unit #3 and Unit #4 on October 27, 2010.

 In the ceremony, Manager Kim Jong-su received a letter of commendation from the minster of knowledge economy and seven employees including Managers Lee Gyeong-hee, Bae Bok-gyu and Lim Jong-hun from the president of Hyundai Green Power.