Completed the Energization at Kayan HDPE site in Saudi Arabia

DATE 2010.05.04

VIEW 451

On April 13, our Kayan HDPE site completed the energization (Substation #25) seventeen days ahead of schedule. Therefore, the site is able to be supplied electricity for the operation of HDPE facilities.

All officials of the site who have found difficulties with preparing the energization celebrated the successful completion of energization, one of big milestones, and pledged to finish the project without any accident. The Saudi Kayan HDPE project started the construction in August 2008 and will be completed the mechanical completion in December 2010.