Applied for a Completion Certificate for the 9 Crude Oil Filling Lines Project in Kuwait
DATE 2009.03.11
VIEW 498
In Feb. 11, Daelim applied for a construction completion certificate for the 9 crude oil filling lines project in Kuwait. The project, started on Dec. 1 2007, holds significance in that it was completed 1.5 months earlier than expected, when compared to the construction progress of Portion 1. The project was designed to replace 60 kilometers of old oil pipelines which connected oil storage tanks in the northern and southern regions of Al-Maqwa field located south of Kuwait City.